FY 2021 Major Projects
Projects in Planning
Bonisteel Boulevard Water Main and Road Reconstruction
Bob and Betty Beyster Building Addition
Central Power Plant Steam Pressure Regulator Valve System
University of Michigan Health System
- Rogel Cancer Center Exterior Improvements
- University Hospital South Roof Replacement
Central Campus Recreation Building Replacement
New Building for College of Pharmacy
Projects in Progress
Catherine Street Area Utility Infrastructure Upgrades | Work started January 2020 with an estimated completion date of September 2021. Financing is from utilities reserves.
Central Power Plant 13,200 Volt Switchgear Upgrade | Work started August 2019 with an estimated completion date of September 2021. Financing is from utilities reserves.
Central Power Plant Expansion | Work started March 2019 with an estimated completion date of September 2021. Financing is from utilities reserves.
Dean Road Transportation Facility | Work started January 2021 with an estimated completion date of September 2022. Financing is from Logistics, Transportation & Parking.
W.K. Kellogg Institute and Dental Building Expansion and Renovation | Work started December 2018 with an estimated completion date of June 2022. Financing is from state capital appropriation, the Office of the Provost, the School of Dentistry and investment proceeds.
Detroit Observatory Classroom and Accessibility Addition | Work started July 2019 with an estimated completion date of July 2021. Financing is from the Bentley Historical Library, gifts and investment proceeds.
Carl A. Gerstacker Building Herbert H. Dow Building Center for Ultrafast Optical Science Expansion | Work started December 2020 with an estimated completion date of March 2022. Financing is from the College of Engineering.
Medical Campus Utility Infrastructure Upgrades | Work started July 2020 with an estimated completion date of December 2021. Financing is from utilities reserves.
University of Michigan Health System | Financing is from the University of Michigan Health System.
- Brighton Center for Specialty Care Central Steam Replacement | Work started December 2020 with an estimated completion date of December 2021.
- Clinical Inpatient Tower | Work restarted May 2021 with an estimated completion date of June 2025.
- University Hospital and University Hospital South Clinical Pathology Laboratories | Work started January 2020 with an estimated completion date of December 2023.
New Dance Building | Work started September 2019 with an estimated completion date of July 2021. Financing is from investment proceeds and the School of Music, Theatre & Dance gifts and resources.
Central Campus Classroom Building and the Alexander G. Ruthven Building Renovation and Addition | Work started December 2018 with an estimated completion date of December 2021. Financing is from investment proceeds.
A. Alfred Taubman Biomedical Science Research Building Vivarium Expansion | Work started February 2021 with an estimated completion date of March 2022. Financing is from the Medical School.
Projects Completed
Alumni Center Renovation | Completed December 2020. Financed by the Alumni Association and gifts.
Dearborn Engineering Lab Building Replacement | Completed February 2021. Financed by state capital appropriation and U-M Dearborn.
Flint William S. White Building Classroom Renovation | Completed March 2021. Financed by UM-Flint.
Flint William R. Murchie Science Building Expansion | Completed March 2021. Financed by state capital appropriation and UM-Flint.
Ford Motor Company Robotics Building | Completed January 2021. Financed by the College of Engineering and gifts.
Hutchins Hall Auditorium 100 Renovation | Completed April 2021. Financed by the Law School and the Office of the Provost.
Edward Henry Kraus Building Renovation and Addition | Completed November 2020. Financed by the Office of the Provost.
Ann and Robert H. Lurie Biomedical Engineering Building First Floor Renovations | Completed December 2020. Financed by the College of Engineering.
University of Michigan Health System | Financed by the University of Michigan Health System.
- 777 East Eisenhower Parkway Leasehold Improvements | Completed August 2020.
- Eisenhower Corporate Park West Homemed Pharmacy Clean Room Renovations | Completed November 2020.
- A. Alfred Taubman Health Care Center Air Handling Equipment Replacement | Completed December 2020.
North Campus Research Complex Buildings 20 and 25 Laboratory Renovation | Completed July 2020. Financed by the Medical School.
South University Pavement and Utility Improvements | Completed December 2020. Financed by the City of Ann Arbor and utilities reserves.
Wall Street West Parking Structure | Completed January 2021. Financed by Logistics, Transportation & Parking.